A511 construction updates and road works

Keep up to date with progress on the project, as well as road and footpath closures and diversions.

Enabling works

Essential enabling works are due to begin at a number of locations along the A511 corridor.

These works are critical to ensure the safe delivery of the scheme and inform future network enhancements, reducing risks and improving long-term road user safety.

To ensure the works can be delivered safely while minimising disruption to road users, temporary traffic management arrangements will be in place at the following locations:

Programme of works 2026

Please note: all dates remain subject to change.

17 and 18 September, Bardon Road Roundabout (8am to 5pm)

  • Temporary footway closure to the first access point on the service road
  • The second access point will remain open throughout the works
  • The utility contractor will undertake utility disconnection works

21 and 22 September, Whitwick Road (Morrisons Roundabout) 10pm to 5am

  • Overnight one-way closure of the roundabout
  • Trial hole investigation works will be undertaken to identify and confirm the location of existing utility services

22 to 26 September, Stephenson Way/Hermitage Road, Hoo Ash and Morrisons Roundabouts (8pm to 5am)

  • Temporary footway closures will be implemented as required
  • Two-way temporary traffic signals will be in operation on 22 September due to lane closures. This is to allow trial hole investigation works to locate existing utility services.

26 October to 11 December, A511 Broom Leys Road, Coalville

BT Openreach will be carrying out work at the A511 Broom Leys Road junction as part of ongoing preparations for the A511 MRN Growth Corridor Scheme.

Temporary traffic lights will be manually controlled between 7am and 7pm Monday to Friday to help keep traffic moving as smoothly as possible. Working hours will be between 8am and 5pm; however, the traffic management will remain in place outside of these hours.

  • 26 October to 13 November: temporary four-way traffic lights 
  • 16 to 27 November: lane closures and narrower lanes 
  • 30 November to 4 December: temporary two-way traffic lights 
  • 7 to 11 December: lane closures 

During this work, expect longer journey times and allow extra time for travel. The work supports the delivery of the A511 improvements, bringing long-term benefits for road users and local communities.

Frequently Asked Questions - A511 Broom Leys Road junction works

Why is this work being carried out?
BT Openreach needs to carry out essential diversionary utility works before the planned A511 improvement scheme can progress. Completing these works now helps prepare the area for future improvements.

Will I see any improvements once this work is finished?
Not immediately. This is preparatory work involving telecommunications infrastructure, so there will be little visible change once the works are complete. However, it's an important step in enabling the future A511 improvement scheme.

Why is traffic management needed?
Traffic management such as temporary traffic lights and lane closures allow the work to be carried out safely while keeping the junction open to traffic, protecting road users and the workforce.

Who is carrying out the work?
The works are being undertaken by MJ Quinn on behalf of BT Openreach as part of the preparations needed to support the delivery of the A511 improvement scheme and its long-term benefits for road users and local communities.

For further Temporary Traffic Regulation Order (TTRO) information, visit Road closures and diversions.