Oadby A6: Crossing and junction safety works

Leicestershire County Council is improving pedestrian and cycle crossing facilities at locations along the A6 corridor in Oadby, centred on The Parade and the Brabazon Road junctions with the A6.

The A6 through Oadby is a busy road that many people need to cross on foot or by bike to reach the town centre, places of worship, shops, and bus stops. We have identified locations where improvements will make the biggest difference to safety.

Latest updates

The first phase of the scheme is progressing as planned and is expected to be completed by the end of November.

The overnight resurfacing of the A6 between The Parade and New Street junction was completed early. There will be no further overnight closures between Monday 23 November and Friday 27 November.

Work completed so far

  • At the Stoughton Road junction, the kerb has been extended into the carriageway, the footway widened, and a raised crossing installed.
  • Raised crossing tables have been installed on Lyndhurst Road.
  • The new permanent traffic signals are now operational.
  • The wider footway and extended kerb at the Stoughton Road junction have made the side road shorter and easier to cross.
  • Improvements have been completed at the south-west corner of The Parade junction.
  • The A6 has been resurfaced between Brabazon Road and New Street.

Work still to be completed

  • Installation of the new seating and planting area at the Regent Street corner.
  • Footway resurfacing between Regent Street and Stoughton Road.
  • Final footway resurfacing on the traffic islands.
  • Remaining road and footway markings.

Planned work

Works started on 3 August 2026 and include:

  • new and upgraded signal-controlled pedestrian and cycle crossings
  • improved crossing facilities at Regent Street, and across Harborough Road / Leicester Road  
  • raised crossings that bring the road up to pavement level on Lyndhurst Road, Stoughton Road, and Victoria Court at their junctions with the A6
  • a raised crossing on the north western section of Oadby Court at its junction with Brabazon Road
  • improvements to footways, including resurfacing 
  • renewal of existing vehicle traffic signals equipment 
  • resurfacing of the road/carriageway between the Brabazon Road and New Street junctions on the A6 
  • new pedestrian and cycle crossing on Brabazon Road

There are no proposed changes to permitted vehicle turning movements, or to the speed limit.

Construction

There will be various traffic management measures in place during the works, including temporary traffic lights and lane closures. At times, closures of some side roads will also be needed to safely facilitate the works.

During the works:

  • Access for refuse collection will be maintained
  • Some bus stops may need to be suspended or relocated for a short time (signs will be posted before any temporary suspension or relocations)
  • Every effort will be made to maintain access to all affected properties throughout the construction period, although there may be delays while work is under way, including during the overnight resurfacing closures (clear signage and staff on site will be present to assist with access and to ensure safety)

notification highlight with information alert

We appreciate your patience while these works are completed.

Phasing

The works will be split into two phases:

Phase 1 – Construction around The Parade junction will start on 3 August 2026 and last for approximately 16 weeks.

Phase 2 – Construction around the Brabazon Road junction will start mid-January 2027 and will complete in early April 2027. Phase 2 designs are being finalised.

Benefits

  • Safer crossings protect everyone on foot and reduce vehicle collisions
  • Raised crossings at side roads improve visibility between drivers and pedestrians, while shorter crossing distances make roads easier and safer to cross
  • Modernised signal equipment with detection ensures vulnerable users are protected and given the time they need to cross safely
  • Traffic signals using visual vehicle detection, rather than induction loops, increase equipment reliability
  • Disruption is minimised by combining the works with planned resurfacing maintenance

Funding

The council was successful in a bid to Active Travel England the government agency within the Department for Transport responsible for promoting walking, wheeling, and cycling.

Active Travel England awarded nearly £900k towards the scheme. We are providing a further £1 million from established active travel budgets. The budget for the scheme is £1.9 million.

Contact

Please email oadbya6@leics.gov.uk with any queries or for further information.

Alternatively, phone 0116 305 0001 with your query and this will be passed to the project team.